Friday, November 21, 2014
1012 C Street  •  Floresville, TX 78114  •  Phone: 830-216-4519  •  Fax: 830-393-3219  • 

WCN Site Search


Lost & Found

If you are missing a pet in Floresville, be sure to check the Floresville holding facility. Animals are only kept for 3 days. Contact Las Lomas K-9 Rescue, 830-581-8041.
Lost: Pug, 1-year-old male, on FM 887 between CR 228 and CR 229, answers to Beaver, (he's bi-lingual), grandkids miss Beaver. Call 210-422-4608. 
Lost: Cats, Gabby is orange and Sammy is white with heart shape on back, missing Oct. 31 off Post Oak Rd., La Vernia, help find them! Call/text 210-315-0266, 210-602-7103.
More Lost & Found ads ›

Help Wanted

The Floresville Independent School District is accepting applications for District Wide Custodian Positions, 2:00 p.m. to 10:30 p.m. shift. Applications may be obtained online at www.fisd.us or contact Sylvia Campa at 830-393-5300 ext. 14002 for appointments. FISD Personnel Office is located at 1200 5th St., Floresville, Texas. 830-393-5300 (Office hours: 8:00-4:00). Applications will be accepted until all positions are filled. An Equal Opportunity Employer.
Experienced horse person wanted to help halter break colts, ground pen work, and riding. Welcome Arabians Ranch, north of Floresville. Call Rita at 210-381-0003. 
More Help Wanted ads ›

Featured Videos





Video Vault ›
WCN your news your way subscribeWCN border security forum 10/30/14WCN printing

Breaking News


CPS: Deely Power Plant Offline Following Silo Explosion




E-Mail this Story to a Friend
Print this Story
Contributed
September 10, 2013, 2:31pm
3,214 views | 2 comments

(San Antonio, TX) - CPS Energy’s 420-megawatt Deely 1 power plant experienced an explosion shortly before 11 a.m. CPS Energy officials quickly worked to evacuate the building and ensure all employees were accounted for and safe.

An initial investigation shows the cascade building -- a part that feeds coal into silos before it’s moved into the plant -- was damaged. The plant’s fire suppression system deployed, working as the safety system should. The plant was online at the time of the explosion, and operators are in the process of taking the plant offline for safety reasons and to investigate further.

Coal is fed into the cascade building by conveyors that move the commodity from coal piles. It is several steps removed from the point at which the coal is burned to make steam and turn a turbine to generate energy. Deely Power Plant is located at a 7,500-acre power station in southeast Bexar County that is owned and operated by the energy company.

CPS Energy is the nation’s largest municipally owned natural gas and electric company, providing service to 741,000 electric and 331,000 natural gas customers in the Greater San Antonio area. The company offers the lowest rates among the top 10 largest U.S. cities, while ranking number one in wind-energy capacity among municipally owned energy systems and number one in Texas for solar generation. For more information, visit www.cpsenergy.com.
 


Your Opinions and Comments

 
New Guy  
Wilson County  
September 10, 2013 10:39pm
 
 
Too bad 4th back yard was not close to this....she wanted EPA rules to be relaxed or done away with.
 
 
Senior Citizen  
Wilson County  
September 10, 2013 10:22pm
 
 
Expect to pay more for our electricity if it stays offline.
 

Share your comment or opinion on this story!


You must be logged in to post comments:



Other Breaking News

omaha-steaks-banner-ads

Connally Memorial MC breaking news banner
Blue Moon Karaoke & DJChester WilsonVoncille Bielefeld homeEast Central Driving SchoolTriple R DC ExpertsHeavenly Touch homeAllstate & McBride Realty

  Copyright © 2007-2014 Wilson County News. All rights reserved. Web development by Drewa Designs.